Hi,

I want to schedule the report at following intervals

9/1 - 11/30
12/1 - 2/28(29) (this is an odd one because of leap years)
3/1 - 5/31
6/1 - 8/31

How can I do this using the cron schedule? Thanks in advance!

Thanks,
Deepthi

0 Karma

somesoni2
Revered Legend

Assuming you want your quarterly report to run as following:

Quarter range     ###   Date on which Report should be run
9/1 - 11/30       ###  12/01 
12/1 - 2/28(29)   ###  03/01
(this is an odd one because of leap years)
3/1 - 5/31        ###   06/01
6/1 - 8/31        ###   09/01

Try the cron schedule as this (running every quarter, as above schedule, at 3 AM in the morning

0 3 1 3,6,9,12 *

Your search's time range would be -3mon@mon to @mon.
See the corresponding scheduled data here: https://crontab.guru/#0_3_1_3,6,9,12_* (click on next hyperlink to see more dates)

0 Karma

FrankVl
Ultra Champion

Is it OK to run the report at midnight of the first day of the next quarter? That would translate to 0 0 1 */3 *.

Then you just need to define the timerange for your report correctly, I guess earliest=-3mon@mon latest=@mon should do the trick?

0 Karma
Get Updates on the Splunk Community!

Archived Metrics Now Available for APAC and EMEA realms

We’re excited to announce the launch of Archived Metrics in Splunk Infrastructure Monitoring for our customers ...

Detecting Remote Code Executions With the Splunk Threat Research Team

WATCH NOWRemote code execution (RCE) vulnerabilities pose a significant risk to organizations. If exploited, ...

Enter the Dashboard Challenge and Watch the .conf24 Global Broadcast!

The Splunk Community Dashboard Challenge is still happening, and it's not too late to enter for the week of ...